What should a scope of work include?
What to put in a scope of work so both sides price, plan and deliver the same job: inclusions, exclusions, assumptions and who supplies what.
A scope of work should say exactly what you will deliver, what you won’t, and what you have assumed about the job. If the scope is unclear, the disagreement about price, timing, quality and variations is just parked for later. It will be harder and costly to resolve.
Scope matters
The scope is the part of the contract everyone uses every day. The contract goes in the drawer. The price, the program and the variation clause all depend on scope. The two parties should not be working from different understandings of the job.
| If the scope is unclear | What usually happens |
|---|---|
| Price | Customer says it was included, you say it is extra |
| Time | Extra work is done without extra time, and you are late |
| Quality | No agreed standard, so “not good enough” is hard to answer |
| Variations | Hard to show what has changed if the starting point isn’t written down, then how do you get paid? |
| Responsibility | Nobody is sure who was meant to supply access, information or approvals |
What to include
- Deliverables: what you will hand over, described so a stranger would understand it.
- Inclusions: the tasks, materials and services covered by the price.
- Exclusions: what is not covered.
- Assumptions: the conditions your price depends on, such as site access, working hours or the number of review rounds, availability of materials supplied by the customer.
- Allowances: amounts set aside for things not yet decided, and what happens if they are exceeded.
- Customer inputs: what the customer must supply, and by when.
- Standards: the specifications, codes or quality you are working to.
- Timing: key dates, milestones and anything that depends on the customer.
Scope should be able to be tested
“Website redesign” is too loose. “Up to 8 pages, 2 rounds of revisions, content supplied by the customer by 31 March” can be checked. Use numbers, lists and limits wherever you can.
Avoid words like “all”, “complete” or “as required” unless you mean them. “All works necessary for a complete installation” could mean you are responsible for excavating sub-surface rocks that prevent laying a slab, when you thought the ground was just dirt.
Link the scope to the rest of the contract
- The price should match the scope, item by item if possible.
- The schedule / programme should match the scope and the customer inputs.
- The variation clause should say that anything outside the scope is a variation. See What is a variation, and why should it be in writing?
- If there are several documents (a proposal, a specification and drawings), say which one wins if they conflict.
In tenders
Buyers expect any conditions affecting your price to be stated in the bid (Business Queensland). If you leave out your assumptions to make the bid look cleaner, you may be stuck with a scope you didn’t price. Also, if you leave out contract departures, you might be taken to have accepted the one-sided tender version. That will probably have a risk pricing impact.
Check before signing
- Could a stranger pick up the document and understand what you are proposing?
- Are exclusions and assumptions written down?
- Does the price line up with the scope?
- Is it clear what the customer has to supply?
- If there is a contract, and your proposal is attached, the contract might say your proposal’s exclusions and assumptions don’t apply. You will need to discuss this because they form the basis of the price.
Templates that help
- Works proposal and Consultant proposal letter: set out scope, assumptions, allowances and exclusions
- Services Agreement and Minor Works Agreement: with a scope schedule and variation process
- Variation claim: when the work goes beyond the scope
This guide is general information, not legal advice for your situation.
